COLORADO SPRINGS, Colo. – As the fifth and final season of 2C paving comes to a close, 1,074 total lane miles have been repaved citywide in Colorado Springs. Crews anticipate completing the final 2C-identified streets – Platte Avenue and Westmeadow Drive – by Saturday, Nov. 21, weather dependent. This work was made possible by the temporary five-year 2C ballot measure passed by voters in 2015 that imposed a 0.62 percent sales tax dedicated exclusively to roadway repairs.
The 2C effort will continue for another five years at a lower sales tax rate (0.57 percent, or 5.7 cents on a $10 purchase), starting Jan. 1, 2021. The sales tax has, on average, collected more than $50 million annually and is expected to continue collecting that amount despite the lower rate. The program's extension was approved by voters in 2019. Necessary pre-overlay work – such as fixing concrete sidewalks, curbs, gutters and pedestrian ramps – has already begun on roads scheduled to be repaved in 2021, the first year of 2C's second five-year term.
"Nothing more clearly defines the renaissance of our city than the significant roadway improvements made possible by ballot measure 2C," said Mayor John Suthers. "While there is still work to be done, funding from this critical local ballot measure has delivered more than the 1,000 lane miles we promised voters when we took this measure to the ballot in 2015. 2C has made a major difference in the trajectory of our critical infrastructure. I am proud of the efficiency of this effort and thank our citizens for their support."
More on Colorado Desk
2C paving occurs in tandem with continued Pikes Peak Rural Transportation Authority (PPRTA) projects that provide routine preventive maintenance to help roads achieve their full life span.
2020 2C paving
The following are paving and concrete milestones funded by 2C specifically in 2020.
2C paving from 2016-2020
The following are cumulative paving and concrete numbers funded by 2C from 2016-2020:
It is expected that additional lane miles will be added to the 1,074 total lane miles from the first five years of 2C in order to exhaust all remaining funds. Locations for this work, to be completed in 2021, are yet to be determined and will depend on sales tax revenue received at the end of 2020.
More on Colorado Desk
Public Works estimates 185 lane miles will be repaved in 2021 as part of the second five-year initiative, and the final list will be released in the coming months. Among the roads slated for 2021 are Interquest Parkway, North Gate Boulevard, Old Farm Circle, Peterson Road, Stetson Hills Boulevard and Weber Street.
With nearly 6,000 lane miles in city limits, the first five years of 2C targeted main roads considered "arterials" and "collectors." The next five years aims to finish the arterials and collectors while also tackling more residential roadways. The order in which roads are paved is dictated by an extensive coordination effort that syncs paving with other roadway projects.
For more information regarding voter-supported 2C projects visit ColoradoSprings.gov/2C.
The 2C effort will continue for another five years at a lower sales tax rate (0.57 percent, or 5.7 cents on a $10 purchase), starting Jan. 1, 2021. The sales tax has, on average, collected more than $50 million annually and is expected to continue collecting that amount despite the lower rate. The program's extension was approved by voters in 2019. Necessary pre-overlay work – such as fixing concrete sidewalks, curbs, gutters and pedestrian ramps – has already begun on roads scheduled to be repaved in 2021, the first year of 2C's second five-year term.
"Nothing more clearly defines the renaissance of our city than the significant roadway improvements made possible by ballot measure 2C," said Mayor John Suthers. "While there is still work to be done, funding from this critical local ballot measure has delivered more than the 1,000 lane miles we promised voters when we took this measure to the ballot in 2015. 2C has made a major difference in the trajectory of our critical infrastructure. I am proud of the efficiency of this effort and thank our citizens for their support."
More on Colorado Desk
- Garage door installation or repair in Minnesota? Which makes more sense for your family?
- MICHELIN Guide Recognizes 15 New Colorado Restaurants
- Super Rooter Expands to 190 Plumbing, Sewer, and Drain Service Locations Across the United States
- European Patent for ALS Program Expands the Story: HOPE Deploys Robotic TMS & FDA Commercialization Path Advances: NRx Pharmaceuticals: NAS DAQ: NRXP
- VICTURY Sports Announces Formation of Youth Sports League Built on the Official, Patented, and Award-Winning Keepy Uppy® Ball
2C paving occurs in tandem with continued Pikes Peak Rural Transportation Authority (PPRTA) projects that provide routine preventive maintenance to help roads achieve their full life span.
2020 2C paving
The following are paving and concrete milestones funded by 2C specifically in 2020.
- Repaved 221 lane miles
- Replaced 188,887 linear feet of curb and gutter
- Replaced 346,112 square feet of sidewalk
- Installed 194 new pedestrian ramps
- Retrofitted 919 existing pedestrian ramps
2C paving from 2016-2020
The following are cumulative paving and concrete numbers funded by 2C from 2016-2020:
- Repaved 1,074 lane miles, the approximate driving distance from Colorado Springs to Chicago
- Replaced 874,131 linear feet of curb and gutter, or 165.5 miles, the approximate driving distance on I-25 from Colorado Springs to the Wyoming border
- Replaced 1,709,693 square feet of sidewalk, the same area as 363 basketball courts
- Installed 880 new pedestrian ramps
- Retrofitted 4,586 existing pedestrian ramps
It is expected that additional lane miles will be added to the 1,074 total lane miles from the first five years of 2C in order to exhaust all remaining funds. Locations for this work, to be completed in 2021, are yet to be determined and will depend on sales tax revenue received at the end of 2020.
More on Colorado Desk
- Congressman Chuck Edwards (NC-11) Presents ReadyCommunities Partnership 2026 National Service Award to Local Businessman / US Air Force Veteran
- Cress Creeks Farm Opens Fall Corn Maze and Baby Lamb Hayride Experience in Ellijay, Georgia
- Allstream Energy Partners Nominated in Multiple Categories for Fast Company's Best Workplaces for Innovators
- Colorado Springs: Hancock Expressway segment closes Sept. 18-Oct. 3 for construction
- Colorado Springs Airport nominated for USA TODAY 10BEST Readers' Choice Award
Public Works estimates 185 lane miles will be repaved in 2021 as part of the second five-year initiative, and the final list will be released in the coming months. Among the roads slated for 2021 are Interquest Parkway, North Gate Boulevard, Old Farm Circle, Peterson Road, Stetson Hills Boulevard and Weber Street.
With nearly 6,000 lane miles in city limits, the first five years of 2C targeted main roads considered "arterials" and "collectors." The next five years aims to finish the arterials and collectors while also tackling more residential roadways. The order in which roads are paved is dictated by an extensive coordination effort that syncs paving with other roadway projects.
For more information regarding voter-supported 2C projects visit ColoradoSprings.gov/2C.
0 Comments
Latest on Colorado Desk
- Governor Polis Celebrates Strong International Partnership at Japan America Society of Colorado Annual Gala
- HydroExcavation.com Relaunches With Exclusive Local Service Areas and Dedicated Hydrovac Manufacturer Directory
- Sky Quarry Enters a Powerful New Chapter: Refinery Restart Emminent, Nevada Oil Initiative and Visibility Put (NAS DAQ: SKYQ) in the Spotlight
- OneVizion Launches Vera AI, Bringing Connected Operational Context to Infrastructure Teams
- P-Wave Press Announces Pushing the Wave 2025 by L.A. Davenport
- DONGSHENG Titanium Recycling: Promoting a Closed-Loop Cycle for High-End Titanium Materials
- Boulder SEO Marketing Founder Takes the Agency Automation Gap to AgencyCon 2026
- Colorado: Bustang Adds On-Demand Visual and ASL Interpreting for Blind, Low Vision, Deaf, and Hard of Hearing Riders
- Supporting Colorado's Cultural Legacy: 25 New Folk and Traditional Arts Initiatives Awarded Across the State
- French Camp Academy Releases New Video Inviting Individuals to Consider a Life of Service
- LET US READ Documentary on Dyslexia and Literacy to Screen at TCL Chinese 6 in Hollywood
- What Colorado Leaders, Communities, and Residents Are Saying About Federal Approval for Public Assistance for Major Disasters
- 303 Crown Maids Enhances Commercial Cleaning Services Page for Local Businesses
- Advanced Precision Machining Unveils New Online Hub for Expert Prototyping, Design, and Drafting Services
- Defense & Space Strategy Strengthens as New Leadership Builds on NASA Results and Expanding Multi-Orbit Opportunities for Ascent Solar Technologies
- STS Capital Partners is pleased to announce the appointment of Barry Brown as Vice President, Business Development
- Qscription Technologies and NEOPATHOLOGY CORP. Sign MOU to Bring FDA-Cleared Lung Imaging AI into U.S. Clinical Practice
- Colorado Springs: Motorcyclist identified in fatal South Union Boulevard crash on August 29, 2026
- Colorado Springs: Nancy Lewis Park marks 30 years with celebration and Wind Phone dedication
- Colorado: Governor Polis Issues Executive Order Expanding the Competency Task Force