COLORADO SPRINGS, Colo. – As the fifth and final season of 2C paving comes to a close, 1,074 total lane miles have been repaved citywide in Colorado Springs. Crews anticipate completing the final 2C-identified streets – Platte Avenue and Westmeadow Drive – by Saturday, Nov. 21, weather dependent. This work was made possible by the temporary five-year 2C ballot measure passed by voters in 2015 that imposed a 0.62 percent sales tax dedicated exclusively to roadway repairs.
The 2C effort will continue for another five years at a lower sales tax rate (0.57 percent, or 5.7 cents on a $10 purchase), starting Jan. 1, 2021. The sales tax has, on average, collected more than $50 million annually and is expected to continue collecting that amount despite the lower rate. The program's extension was approved by voters in 2019. Necessary pre-overlay work – such as fixing concrete sidewalks, curbs, gutters and pedestrian ramps – has already begun on roads scheduled to be repaved in 2021, the first year of 2C's second five-year term.
"Nothing more clearly defines the renaissance of our city than the significant roadway improvements made possible by ballot measure 2C," said Mayor John Suthers. "While there is still work to be done, funding from this critical local ballot measure has delivered more than the 1,000 lane miles we promised voters when we took this measure to the ballot in 2015. 2C has made a major difference in the trajectory of our critical infrastructure. I am proud of the efficiency of this effort and thank our citizens for their support."
More on Colorado Desk
2C paving occurs in tandem with continued Pikes Peak Rural Transportation Authority (PPRTA) projects that provide routine preventive maintenance to help roads achieve their full life span.
2020 2C paving
The following are paving and concrete milestones funded by 2C specifically in 2020.
2C paving from 2016-2020
The following are cumulative paving and concrete numbers funded by 2C from 2016-2020:
It is expected that additional lane miles will be added to the 1,074 total lane miles from the first five years of 2C in order to exhaust all remaining funds. Locations for this work, to be completed in 2021, are yet to be determined and will depend on sales tax revenue received at the end of 2020.
More on Colorado Desk
Public Works estimates 185 lane miles will be repaved in 2021 as part of the second five-year initiative, and the final list will be released in the coming months. Among the roads slated for 2021 are Interquest Parkway, North Gate Boulevard, Old Farm Circle, Peterson Road, Stetson Hills Boulevard and Weber Street.
With nearly 6,000 lane miles in city limits, the first five years of 2C targeted main roads considered "arterials" and "collectors." The next five years aims to finish the arterials and collectors while also tackling more residential roadways. The order in which roads are paved is dictated by an extensive coordination effort that syncs paving with other roadway projects.
For more information regarding voter-supported 2C projects visit ColoradoSprings.gov/2C.
The 2C effort will continue for another five years at a lower sales tax rate (0.57 percent, or 5.7 cents on a $10 purchase), starting Jan. 1, 2021. The sales tax has, on average, collected more than $50 million annually and is expected to continue collecting that amount despite the lower rate. The program's extension was approved by voters in 2019. Necessary pre-overlay work – such as fixing concrete sidewalks, curbs, gutters and pedestrian ramps – has already begun on roads scheduled to be repaved in 2021, the first year of 2C's second five-year term.
"Nothing more clearly defines the renaissance of our city than the significant roadway improvements made possible by ballot measure 2C," said Mayor John Suthers. "While there is still work to be done, funding from this critical local ballot measure has delivered more than the 1,000 lane miles we promised voters when we took this measure to the ballot in 2015. 2C has made a major difference in the trajectory of our critical infrastructure. I am proud of the efficiency of this effort and thank our citizens for their support."
More on Colorado Desk
- "BigPirate" Sets Sail: A New Narrative-Driven Social Casino Adventure
- Phinge CEO Ranked #1 Globally by Crunchbase for the Last Week, Will Be in Las Vegas Jan. 4-9, the Week of CES to Discuss Netverse & IPO Coming in 2026
- Colorado: Governor Polis Makes Appointments in the 6th Judicial District
- Women's Everyday Safety Is Changing - The Blue Luna Shows How
- Microgaming Unveils Red Papaya: A New Studio Delivering Cutting-Edge, Feature-Rich Slots
2C paving occurs in tandem with continued Pikes Peak Rural Transportation Authority (PPRTA) projects that provide routine preventive maintenance to help roads achieve their full life span.
2020 2C paving
The following are paving and concrete milestones funded by 2C specifically in 2020.
- Repaved 221 lane miles
- Replaced 188,887 linear feet of curb and gutter
- Replaced 346,112 square feet of sidewalk
- Installed 194 new pedestrian ramps
- Retrofitted 919 existing pedestrian ramps
2C paving from 2016-2020
The following are cumulative paving and concrete numbers funded by 2C from 2016-2020:
- Repaved 1,074 lane miles, the approximate driving distance from Colorado Springs to Chicago
- Replaced 874,131 linear feet of curb and gutter, or 165.5 miles, the approximate driving distance on I-25 from Colorado Springs to the Wyoming border
- Replaced 1,709,693 square feet of sidewalk, the same area as 363 basketball courts
- Installed 880 new pedestrian ramps
- Retrofitted 4,586 existing pedestrian ramps
It is expected that additional lane miles will be added to the 1,074 total lane miles from the first five years of 2C in order to exhaust all remaining funds. Locations for this work, to be completed in 2021, are yet to be determined and will depend on sales tax revenue received at the end of 2020.
More on Colorado Desk
- BOHO Design Rentals Launches Luxury Sofa Rentals in Denver
- Adam's Plumbing & Heating Unveils the Ultimate Lakewood Plumbing Repair & Installation Resource for Homeowners and Businesses
- Five New Proposition 123 Equity Program Selections to Support Housing Coloradans Can Afford Across Colorado
- 5-Star Duncan Injury Group Expands Personal Injury Representation to Arizona
- The End of "Influencer" Gambling: Bonusetu Analyzes Finland's Strict New Casino Marketing Laws
Public Works estimates 185 lane miles will be repaved in 2021 as part of the second five-year initiative, and the final list will be released in the coming months. Among the roads slated for 2021 are Interquest Parkway, North Gate Boulevard, Old Farm Circle, Peterson Road, Stetson Hills Boulevard and Weber Street.
With nearly 6,000 lane miles in city limits, the first five years of 2C targeted main roads considered "arterials" and "collectors." The next five years aims to finish the arterials and collectors while also tackling more residential roadways. The order in which roads are paved is dictated by an extensive coordination effort that syncs paving with other roadway projects.
For more information regarding voter-supported 2C projects visit ColoradoSprings.gov/2C.
0 Comments
Latest on Colorado Desk
- LaTerra and Respark Under Contract with AIMCO to Acquire a $455M, 7-Property Chicago Multifamily Portfolio
- Record Revenue, Tax Tailwinds, and AI-Driven Scale: Why Off The Hook YS Inc. Is Emerging as a Standout in the $57 Billion U.S. Marine Market
- VSee Health (N A S D A Q: VSEE) Secures $6.0M At-Market Investment, Accelerates Expansion as Revenues Surge
- Children Rising Appoints Marshelle A. Wilburn as New Executive Director
- Fairmint CEO Joris Delanoue Elected General Director of the Canton Foundation
- Sleep Basil Mattress Co.'s Debuts New Home Page Showcasing Performance Sleep Solutions for Active Denver Lifestyles
- Bent Danholm Joins The American Dream TV as Central Florida Host
- Powers Dental Group Expands Full‑Spectrum Dental Treatment Services in Colorado Springs
- The Nature of Miracles Celebrates 20th Anniversary Third Edition Published by DreamMakers Enterprises LLC
- Colorado Springs: Overnight lane closures Tuesday and Wednesday on Garden of the Gods Road
- Colorado Springs: Bridge beam placements to impact 8th Street traffic starting Tuesday
- Artificial Intelligence Leader Releases Children's Book on Veterans Day
- Colorado: Governor Polis Shares Information on Pine Beetle Outbreak, Announces New Task Force to Help Communities, Forests, and Water Resources
- Governor Polis Announces JB Holston as the Next Executive Director of Colorado Department of Higher Education
- Felicia Allen Hits #1 Posthumously with "Christmas Means Worship"
- The School of Reps Joins Rural Jump-Start Program, Plans Indoor Athletic Training Facility in Sterling to Serve Northeastern Colorado
- CCHR Documentary Probes Growing Evidence Linking Psychiatric Drugs to Violence
- Governor Polis, Colorado Parks and Wildlife, and Great Outdoors Colorado Award $9.99 Million to Projects Advancing Colorado's Outdoors Strategy
- Associates in Forensic Investigations Newsletter - Nexus of Crime Scenes and Autopsies – Dec 2025
- Mend Colorado Launches Enhanced Personal Training Resource for Lafayette Residents